Strawberry Farm
QAIR RENEWABLES UK LIMITED at North Anglia Connection Node D 132kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 278 MW
- Connected now
- 0 MW
- Still to connect
- 278 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-005077
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Jun 2026 registerMarked as Gate 1
- 5 Jun 2026 registerConnection point changed from Walpole GSP (EPN) to North Anglia Connection Node D 132kV Substation
- 27 Jun 2025 registerAdded to the register
Also at North Anglia Connection Node D 132kV Substation
Substation view1 other project, 478 MW still to connect at this substation in total.