Red Moss Farm
QAIR RENEWABLES UK LIMITED at Red Moss Farm 132kV Substation
- Connection date
- 30 May 2031 +7 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Granted 19 Jun 2025
Scottish Government (S36), reference ECU00005043 · Source: REPD - Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002613
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Oct 2030 to 30 May 2031 (+7 months)
- 1 May 2026 registerMarked as Gate 1
- 31 Jan 2025 registerConnection point changed from Red Moss GSP to Red Moss Farm 132kV Substation
- 24 Dec 2024 registerCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- 29 Aug 2023 registerAdded to the register
Also at Red Moss Farm 132kV Substation
Substation viewNo other projects in the register at this connection point.