- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004269
- In the register since
- November 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Oct 2038 to 31 Oct 2034 (−48 months)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2034 to 30 Oct 2038 (+48 months)
- 12 Dec 2025 registerMarked as Gate 1
- 31 Jan 2025 registerConnection point changed from South Anglia Connection Node E 400kV Substation to East Anglia Connection Node E 400kV Substation
- 24 Dec 2024 registerCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- 24 Dec 2024 registerConnection point changed from Sizewell 400kV Substation to South Anglia Connection Node E 400kV Substation
- 24 Dec 2024 registerConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
- 26 Nov 2024 registerAdded to the register
Also at East Anglia Connection Node E 400kV Substation
Substation viewNo other projects in the register at this connection point.