Keadby Generation Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Ferrybridge D | Ferrybridge C 275kV Substation | Thermal (gas, biomass, waste) | 1,420 | 4 Oct 2030 | Not stated | Scoping |
| Keadby North Power Station | Keadby 400kV Substation | Thermal (gas, biomass, waste) | 892 | 31 Oct 2031 | Not stated | Awaiting Consents |
| Keadby South Power Station | Keadby 400kV Substation | Thermal (gas, biomass, waste) | 155 | 30 Apr 2034 | Not stated | Built |
| Protos Power Station | MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION | Thermal (gas, biomass, waste) | 910 | 1 Nov 2037 | Gate 1 | Scoping |
| Keadby II | Keadby 400kV Substation | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Left the register since January 2021: Keadby (0 MW), Fiddlers Ferry (0 MW).
Recent changes
- KeadbyEngland and Wales, Thermal (gas, biomass, waste)Left the register (910 MW connected)0 MW
- Protos Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Elton 400kV Substation to MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION
- Protos Power StationEngland and Wales, Thermal (gas, biomass, waste)Marked as Gate 1
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Capacity changed from 310 MW to 1,220 MW
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Capacity changed from 910 MW to 200 MW
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 4 Oct 2030 to 1 Jun 2034 (+44 months)+44 mo
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage removed (200 MW from 1 Jun 2034)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Connection date moved from 6 Oct 2028 to 4 Oct 2030 (+24 months)+24 mo
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Technology changed from Gas (CCGT), Demand, Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT), Hydrogen
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Technology changed from Gas (CCGT), Demand, Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT), Hydrogen
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (600 MW from 1 Jun 2034) to 1 stage (200 MW from 1 Jun 2034)
- KeadbyEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 3: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- KeadbyEngland and Wales, Thermal (gas, biomass, waste)Left the register (755 MW connected + 155 MW from 1 Oct 2026)155 MW
- Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)755 MW now connectedConnected
- Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Oct 2026 to 30 Apr 2034 (+91 months)+91 mo
- Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Status changed from Scoping to Built
- Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Renamed from Keadby 3
- Keadby North Power StationEngland and Wales, Thermal (gas, biomass, waste)Renamed from Keadby Hydrogen
- Protos Power StationEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 3: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (1,820 MW from 1 Sep 2026) to 3 stages (310 MW from 6 Oct 2028, 910 MW from 4 Oct 2030, 600 MW from 1 Jun 2034). First connection date +25 months+25 mo
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Ferrybridge GSP to Ferrybridge C 275kV Substation
- KeadbyEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Keadby GSP to Keadby 400kV Substation
- Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Keadby GSP to Keadby 400kV Substation
- Keadby North Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Keadby GSP to Keadby 400kV Substation
- Keadby North Power StationEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Ferrybridge to Ferrybridge GSP)
- KeadbyEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Keadby to Keadby GSP)
- Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Keadby to Keadby GSP)
- KeadbyEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 0 MW to 155 MW
- KeadbyEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 1 Oct 2026
- Keadby IIEngland and Wales, Thermal (gas, biomass, waste)893 MW now connectedConnected
- Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Status changed from Consents Approved to Built
- Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 22 Jun 2021 to 22 Oct 2021 (+4 months)+4 mo
- Fiddlers FerryEngland and Wales, Thermal (gas, biomass, waste)Left the register (0 MW)0 MW
- Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 30 Dec 2020 to 22 Jun 2021 (+6 months)+6 mo
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 9 Jan 2026 to 1 Sep 2026 (+8 months)+8 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose