Ferrybridge C 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Ferrybridge D | Keadby Generation Limited | Thermal (gas, biomass, waste) | 1,420 | 4 Oct 2030 | Not stated | Scoping |
| Ferrybridge C PV & BESS Substation | O&G Solar (SPV 19) Limited | Storage with solar or wind | 250 | 24 Oct 2035 | Not stated | Scoping |
Recent changes
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Capacity changed from 310 MW to 1,220 MW
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Capacity changed from 910 MW to 200 MW
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 4 Oct 2030 to 1 Jun 2034 (+44 months)+44 mo
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage removed (200 MW from 1 Jun 2034)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Connection date moved from 6 Oct 2028 to 4 Oct 2030 (+24 months)+24 mo
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Technology changed from Gas (CCGT), Demand, Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT), Hydrogen
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Technology changed from Gas (CCGT), Demand, Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT), Hydrogen
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (600 MW from 1 Jun 2034) to 1 stage (200 MW from 1 Jun 2034)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 3: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Stage 3: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- Ferrybridge C PV & BESS SubstationEngland and Wales, Storage with solar or windAdded to the registerNew
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (1,820 MW from 1 Sep 2026) to 3 stages (310 MW from 6 Oct 2028, 910 MW from 4 Oct 2030, 600 MW from 1 Jun 2034). First connection date +25 months+25 mo
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Ferrybridge GSP to Ferrybridge C 275kV Substation
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Ferrybridge to Ferrybridge GSP)
- Ferrybridge DEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 9 Jan 2026 to 1 Sep 2026 (+8 months)+8 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?