Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Keadby 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
1 GWstill to connect
0 MWof that with Gate 2 offers
1.7 GWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Keadby North Power StationKeadby Generation LimitedThermal (gas, biomass, waste)89231 Oct 2031Not statedAwaiting Consents
Keadby South Power StationKeadby Generation LimitedThermal (gas, biomass, waste)15530 Apr 2034Not statedBuilt
BriggCBS ENERGY STORAGE ASSETS UK LIMITEDThermal (gas, biomass, waste)0ConnectedNot statedBuilt
Keadby IIKeadby Generation LimitedThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Left the register since January 2021: Keadby (0 MW).

Recent changes

  • KeadbyEngland and Wales, Thermal (gas, biomass, waste)Left the register (910 MW connected)0 MW
  • KeadbyEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
  • KeadbyEngland and Wales, Thermal (gas, biomass, waste)Left the register (755 MW connected + 155 MW from 1 Oct 2026)155 MW
  • Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)755 MW now connectedConnected
  • Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Oct 2026 to 30 Apr 2034 (+91 months)+91 mo
  • Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Status changed from Scoping to Built
  • Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Renamed from Keadby 3
  • Keadby North Power StationEngland and Wales, Thermal (gas, biomass, waste)Renamed from Keadby Hydrogen
  • BriggEngland and Wales, Thermal (gas, biomass, waste)Customer changed from CENTRICA BRIGG LIMITED to CBS ENERGY STORAGE ASSETS UK LIMITED
  • Keadby South Power StationEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
  • KeadbyEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Keadby GSP to Keadby 400kV Substation
  • Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Keadby GSP to Keadby 400kV Substation
  • Keadby North Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Keadby GSP to Keadby 400kV Substation
  • Keadby North Power StationEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
  • BriggEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Keadby 400kV to Keadby 400kV Substation)
  • KeadbyEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Keadby to Keadby GSP)
  • Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Keadby to Keadby GSP)
  • KeadbyEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 0 MW to 155 MW
  • KeadbyEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 1 Oct 2026
  • Keadby IIEngland and Wales, Thermal (gas, biomass, waste)893 MW now connectedConnected
  • Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Status changed from Consents Approved to Built
  • Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 22 Jun 2021 to 22 Oct 2021 (+4 months)+4 mo
  • Keadby IIEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 30 Dec 2020 to 22 Jun 2021 (+6 months)+6 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO