QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Keadby II

Keadby Generation Limited at Keadby 400kV Substation

Connection date
Connected
Gate
Not stated
Status
Built
Technology
Gas (CCGT)
Total capacity
893 MW
Connected now
893 MW
Still to connect
0 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000310
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 28 Feb 2023 register
    Connection point changed from Keadby GSP to Keadby 400kV Substation
  • 29 Nov 2022 register
    Substation name updated in the register (from Keadby to Keadby GSP)
  • 30 Nov 2021 register
    893 MW now connected
  • 30 Nov 2021 register
    Status changed from Consents Approved to Built
  • 29 Oct 2021 register
    Connection date moved from 22 Jun 2021 to 22 Oct 2021 (+4 months)
  • 30 Mar 2021 register
    Connection date moved from 30 Dec 2020 to 22 Jun 2021 (+6 months)

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO