Protos Power Station
Keadby Generation Limited at MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION
- Connection date
- 1 Nov 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Gas (CCGT)
- Total capacity
- 910 MW
- Connected now
- 0 MW
- Still to connect
- 910 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002823
- In the register since
- September 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Mar 2026 registerConnection point changed from Elton 400kV Substation to MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION
- 27 Mar 2026 registerMarked as Gate 1
- 29 Sep 2023 registerAdded to the register
Also at MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION
Substation view1 other project, 1.3 GW still to connect at this substation in total. 350 MW is due to connect here before this project’s connection date of 1 Nov 2037.