Keadby North Power Station
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Gas (CCGT)
- Total capacity
- 892 MW
- Connected now
- 0 MW
- Still to connect
- 892 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001980
- In the register since
- January 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Dec 2024 registerRenamed from Keadby Hydrogen
- 28 Feb 2023 registerConnection point changed from Keadby GSP to Keadby 400kV Substation
- 31 Jan 2023 registerAdded to the register
Also at Keadby 400kV Substation
Substation view3 other projects, 1 GW still to connect at this substation in total.