Monk Fryston 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Monk Fryston SSE | SSE BATTERY MONK FRYSTON LIMITED | Storage | 320 | 31 Oct 2025 Past date | Not stated | Consents Approved |
| Monk Fryston BESS | HARMONY MF LIMITED | Storage | 200 | 31 Oct 2029 | Not stated | Scoping |
| Monk Fryston | Downing Renewable Developments LLP | Storage | 250 | 30 Oct 2035 | Gate 1 | Scoping |
| Kingfisher Farm | REWE 6 LIMITED | Storage | 200 | 2 Jun 2036 | Gate 1 | Scoping |
| Monk Fryston Tertiary Connection | HD777FRY LTD | Storage | 0 | Connected | Not stated | Built |
Recent changes
- Kingfisher FarmEngland and Wales, StorageMarked as Gate 1
- Kingfisher FarmEngland and Wales, StorageGate marking removed (was Gate 1)
- Kingfisher FarmEngland and Wales, StorageMarked as Gate 1
- Monk FrystonEngland and Wales, StorageMarked as Gate 1
- Monk Fryston Tertiary ConnectionEngland and Wales, Storage57 MW now connectedConnected
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageStatus changed from Consents Approved to Built
- Monk FrystonEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- Monk Fryston BESSEngland and Wales, StorageCustomer changed from HARMONY ENERGY LIMITED to HARMONY MF LIMITED
- Kingfisher FarmEngland and Wales, StorageCustomer changed from CSWE 6 LIMITED to REWE 6 LIMITED
- Monk FrystonEngland and Wales, StorageAdded to the registerNew
- Monk Fryston SSEEngland and Wales, StorageConnection date moved from 31 Oct 2024 to 31 Oct 2025 (+12 months)+12 mo
- Kingfisher FarmEngland and Wales, StorageAdded to the registerNew
- Monk Fryston SSEEngland and Wales, StorageRenamed from Monk Fryston BESS
- Monk Fryston SSEEngland and Wales, StorageCustomer changed from UKPA ENERGYMF LTD to SSE BATTERY MONK FRYSTON LIMITED
- Monk Fryston SSEEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageSubstation name updated in the register (from Monk Fryston GSP to Monk Fryston 275kV Substation)
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageTechnology changed from Gas engines to Storage
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageConnection date moved from 31 Oct 2023 to 1 Oct 2024 (+11 months)+11 mo
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Monk Fryston BESSEngland and Wales, StorageAdded to the registerNew
- Monk Fryston SSEEngland and Wales, StorageSubstation name updated in the register (from Monk Fryston to Monk Fryston 275kV Substation)
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageSubstation name updated in the register (from Monk Fryston to Monk Fryston GSP)
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageCapacity changed from 49.9 MW to 57 MW
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageConnection date moved from 1 Oct 2022 to 31 Oct 2023 (+13 months)+13 mo
- Monk Fryston SSEEngland and Wales, StorageAdded to the registerNew
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?