Monk Fryston Tertiary Connection
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted on appeal 1 Aug 2022
North Yorkshire, reference 2021/0633/FULM · Source: REPD - Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 57 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000479
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 register57 MW now connected
- 29 Jul 2025 registerStatus changed from Consents Approved to Built
- 28 Feb 2023 registerSubstation name updated in the register (from Monk Fryston GSP to Monk Fryston 275kV Substation)
- 28 Feb 2023 registerTechnology changed from Gas engines to Storage
- 29 Nov 2022 registerConnection date moved from 31 Oct 2023 to 1 Oct 2024 (+11 months)
- 30 Sep 2022 registerStatus changed from Scoping to Consents Approved
- 30 Mar 2022 registerSubstation name updated in the register (from Monk Fryston to Monk Fryston GSP)
- 28 Sep 2021 registerCapacity changed from 49.9 MW to 57 MW
- 28 Sep 2021 registerConnection date moved from 1 Oct 2022 to 31 Oct 2023 (+13 months)
- 26 Feb 2021 registerConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)
Also at Monk Fryston 275kV Substation
Substation view4 other projects, 970 MW still to connect at this substation in total.