Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Downing Renewable Developments LLP

Customer named in the TEC register

8projects in the register
2.9 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Rat Hall SolarBurwell South 400kV SubstationStorage with solar or wind20031 Oct 2032Gate 1Scoping
Ashbrook Lane BESSWEST ANGLIA CONNECTION NODE B 400KV SUBSTATIONStorage25031 Oct 2034 +36 moGate 1Scoping
FCC Thurcroft BESSLeeds North Connection Node C 400kV SubstationStorage75030 Oct 2035 +24 moGate 1Scoping
Monk FrystonMonk Fryston 275kV SubstationStorage25030 Oct 2035Gate 1Scoping
Jackdaw BESSLeeds North Connection Node B 400kV SubstationStorage25031 Oct 2035 −12 moGate 1Scoping
Caegarw FarmMargam B 400kV SubstationStorage with solar or wind35010 May 2037 +2 moGate 1Scoping
Didcot BESS 1Chiltern Connection Node A 400kV SubstationStorage75031 Oct 2037Gate 1Scoping
Didcot BESS 2Didcot 132kV GIS SubstationStorage99.931 Oct 2037Gate 1Scoping

Recent changes

  • FCC Thurcroft BESSEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
  • Jackdaw BESSEngland and Wales, StorageConnection date moved from 31 Oct 2036 to 31 Oct 2035 (−12 months)−12 mo
  • Jackdaw BESSEngland and Wales, StorageMarked as Gate 1
  • FCC Thurcroft BESSEngland and Wales, StorageConnection date moved from 30 Oct 2035 to 31 Oct 2033 (−24 months)−24 mo
  • Ashbrook Lane BESSEngland and Wales, StorageConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)+36 mo
  • Ashbrook Lane BESSEngland and Wales, StorageMarked as Gate 1
  • Caegarw FarmEngland and Wales, Storage with solar or windConnection date moved from 10 Mar 2037 to 10 May 2037 (+2 months)+2 mo
  • FCC Thurcroft BESSEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
  • Didcot BESS 1England and Wales, StorageConnection point changed from Didcot 400kV Substation to Chiltern Connection Node A 400kV Substation
  • Didcot BESS 1England and Wales, StorageMarked as Gate 1
  • FCC Thurcroft BESSEngland and Wales, StorageConnection point changed from Thorpe Marsh GSP to Leeds North Connection Node C 400kV Substation
  • FCC Thurcroft BESSEngland and Wales, StorageMarked as Gate 1
  • Caegarw FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Rat Hall SolarEngland and Wales, Storage with solar or windMarked as Gate 1
  • Didcot BESS 2England and Wales, StorageConnection point changed from Didcot GSP to Didcot 132kV GIS Substation
  • Didcot BESS 2England and Wales, StorageMarked as Gate 1
  • Monk FrystonEngland and Wales, StorageMarked as Gate 1
  • Ashbrook Lane BESSEngland and Wales, StorageConnection point changed from Wymondley GSP to WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION
  • Caegarw FarmEngland and Wales, Storage with solar or windConnection point changed from Pyle 275kV Substation to Margam B 400kV Substation
  • Caegarw FarmEngland and Wales, Storage with solar or windConnection date moved from 10 May 2037 to 10 Mar 2037 (−2 months)−2 mo
  • Monk FrystonEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
  • Jackdaw BESSEngland and Wales, StorageConnection point changed from New Stutton LILO 275kV Substation to Leeds North Connection Node B 400kV Substation
  • Monk FrystonEngland and Wales, StorageAdded to the registerNew
  • Didcot BESS 1England and Wales, StorageAdded to the registerNew
  • Didcot BESS 2England and Wales, StorageAdded to the registerNew
  • FCC Thurcroft BESSEngland and Wales, StorageAdded to the registerNew
  • Jackdaw BESSEngland and Wales, StorageAdded to the registerNew
  • Ashbrook Lane BESSEngland and Wales, StorageAdded to the registerNew
  • Caegarw FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Rat Hall SolarEngland and Wales, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO