HD777FRY LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Monk Fryston Tertiary Connection | Monk Fryston 275kV Substation | Storage | 0 | Connected | Not stated | Built |
Recent changes
- Monk Fryston Tertiary ConnectionEngland and Wales, Storage57 MW now connectedConnected
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageStatus changed from Consents Approved to Built
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageSubstation name updated in the register (from Monk Fryston GSP to Monk Fryston 275kV Substation)
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageTechnology changed from Gas engines to Storage
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageConnection date moved from 31 Oct 2023 to 1 Oct 2024 (+11 months)+11 mo
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageSubstation name updated in the register (from Monk Fryston to Monk Fryston GSP)
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageCapacity changed from 49.9 MW to 57 MW
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageConnection date moved from 1 Oct 2022 to 31 Oct 2023 (+13 months)+13 mo
- Monk Fryston Tertiary ConnectionEngland and Wales, StorageConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?