Monk Fryston SSE
SSE BATTERY MONK FRYSTON LIMITED at Monk Fryston 275kV Substation
- Connection date
- 31 Oct 2025
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted on appeal 1 Dec 2022
North Yorkshire, reference 2021/0789/FULM · Source: REPD - Technology
- Storage
- Total capacity
- 320 MW
- Connected now
- 0 MW
- Still to connect
- 320 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001627
- In the register since
- August 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Nov 2023 registerConnection date moved from 31 Oct 2024 to 31 Oct 2025 (+12 months)
- 28 Feb 2023 registerRenamed from Monk Fryston BESS
- 28 Feb 2023 registerCustomer changed from UKPA ENERGYMF LTD to SSE BATTERY MONK FRYSTON LIMITED
- 28 Feb 2023 registerStatus changed from Scoping to Consents Approved
- 30 Mar 2022 registerSubstation name updated in the register (from Monk Fryston to Monk Fryston 275kV Substation)
- 31 Aug 2021 registerAdded to the register
Also at Monk Fryston 275kV Substation
Substation view4 other projects, 970 MW still to connect at this substation in total.