Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Lovedean 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
356 MWstill to connect
0 MWof that with Gate 2 offers
20 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Lovedean Greener Grid ParkStatkraft UK LtdStorage49.91 Jun 2028Gate 1Scoping
Lovedean (Tertiary)LOVEDEAN GREEN LIMITEDStorage with solar or wind5730 Oct 2029Not statedScoping
EcoLovedeanEconergy International LimitedStorage24931 Mar 2031Gate 1Scoping
Green Frog @ Down Barn FarmVIRIDIS 178 LIMITEDThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

  • EcoLovedeanEngland and Wales, StorageMarked as Gate 1
  • Lovedean Greener Grid ParkEngland and Wales, StorageMarked as Gate 1
  • Lovedean (Tertiary)England and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 30 Jul 2024, 7.1 MW from 30 May 2025) to 1 stage (57 MW from 30 Oct 2029). First connection date +63 months+63 mo
  • Lovedean Greener Grid ParkEngland and Wales, StorageRestructured from 2 stages (0 MW from 1 Jun 2024, 49.9 MW from 1 Jun 2026) to 1 stage (49.9 MW from 1 Jun 2028). First connection date +24 months+24 mo
  • EcoLovedeanEngland and Wales, StorageSubstation name updated in the register (from Lovedean 400kV to Lovedean 400kV Substation)
  • Green Frog @ Down Barn FarmEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Lovedean 400kV to Lovedean 400kV Substation)
  • Lovedean (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Lovedean 400kV to Lovedean 400kV Substation)
  • Lovedean Greener Grid ParkEngland and Wales, StorageSubstation name updated in the register (from Lovedean 400kV to Lovedean 400kV Substation)
  • EcoLovedeanEngland and Wales, StorageAdded to the registerNew
  • Lovedean Greener Grid ParkEngland and Wales, StorageAdded to the registerNew
  • Lovedean (Tertiary)England and Wales, Storage with solar or windStage 1: Connection date moved from 30 Jun 2023 to 30 Jul 2024 (+13 months)+13 mo
  • Lovedean (Tertiary)England and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2023 to 30 May 2025 (+19 months)+19 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO