EcoLovedean
- Connection date
- 31 Mar 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002230
- In the register since
- November 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 17 Apr 2026 registerMarked as Gate 1
- 23 Dec 2022 registerSubstation name updated in the register (from Lovedean 400kV to Lovedean 400kV Substation)
- 29 Nov 2022 registerAdded to the register
Also at Lovedean 400kV Substation
Substation view3 other projects, 356 MW still to connect at this substation in total. 107 MW is due to connect here before this project’s connection date of 31 Mar 2031.