Lovedean (Tertiary)
- Connection date
- 30 Oct 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000484
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 registerRestructured from 2 stages (49.9 MW from 30 Jul 2024, 7.1 MW from 30 May 2025) to 1 stage (57 MW from 30 Oct 2029). First connection date +63 months
- 23 Dec 2022 registerSubstation name updated in the register (from Lovedean 400kV to Lovedean 400kV Substation)
- 31 May 2022 registerStage 1: Connection date moved from 30 Jun 2023 to 30 Jul 2024 (+13 months)
- 31 May 2022 registerStage 2: Connection date moved from 31 Oct 2023 to 30 May 2025 (+19 months)
Also at Lovedean 400kV Substation
Substation view3 other projects, 356 MW still to connect at this substation in total. 49.9 MW is due to connect here before this project’s connection date of 30 Oct 2029.