Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Kingsnorth 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
2.8 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Cuxton 49.5MW BESSCuxton Energy Storage LimitedStorage49.531 May 2023 Past dateNot statedConsents Approved
Damhead Creek 2VPI Power LimitedThermal (gas, biomass, waste)1,80031 Oct 2030 +62 moNot statedConsents Approved
Kingsnorth BESS NPNORIKER POWER LTDStorage50031 Dec 2030 −22 moGate 1Scoping
Medway 3 Power StationMEDWAY POWER LIMITEDStorage50030 Apr 2032 +16 moGate 1Scoping

Recent changes

  • Kingsnorth BESS NPEngland and Wales, StorageConnection date moved from 29 Oct 2032 to 31 Dec 2030 (−22 months)−22 mo
  • Medway 3 Power StationEngland and Wales, StorageConnection date moved from 31 Dec 2030 to 30 Apr 2032 (+16 months)+16 mo
  • Medway 3 Power StationEngland and Wales, StorageMarked as Gate 1
  • Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Connection date moved from 31 Aug 2025 to 31 Oct 2030 (+62 months)+62 mo
  • Kingsnorth BESS NPEngland and Wales, StorageMarked as Gate 1
  • Medway 3 Power StationEngland and Wales, StorageTechnology changed from Gas (CCGT), Storage to Demand, LAES (Liquid Air Energy Storage)
  • Medway 3 Power StationEngland and Wales, StorageTechnology changed from Gas (OCGT) to Gas (CCGT), Storage
  • Medway 3 Power StationEngland and Wales, StorageConnection point changed from Grain 400kV Substation to Kingsnorth 400kV Substation
  • Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
  • Kingsnorth BESS NPEngland and Wales, StorageAdded to the registerNew
  • Cuxton 49.5MW BESSEngland and Wales, StorageConnection point changed from Kingsnorth 132kV Substation to Kingsnorth 400kV Substation
  • Medway 3 Power StationEngland and Wales, StorageAdded to the registerNew
  • Cuxton 49.5MW BESSEngland and Wales, StorageSubstation name updated in the register (from Kingsnorth 132kV to Kingsnorth 132kV Substation)
  • Cuxton 49.5MW BESSEngland and Wales, StorageConnection point changed from Kingsnorth 13kV to Kingsnorth 132kV
  • Cuxton 49.5MW BESSEngland and Wales, StorageAdded to the registerNew
  • Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Kingsnorth 400kV to Kingsnorth 400kV Substation)
  • Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Connection date moved from 31 Aug 2024 to 31 Aug 2025 (+12 months)+12 mo
  • Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Connection date moved from 30 Sep 2022 to 31 Aug 2024 (+23 months)+23 mo
  • Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Customer changed from DRAX GENERATION ENTERPRISE LIMITED to VPI POWER LIMITED
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO