Kingsnorth BESS NP
- Connection date
- 31 Dec 2030 −22 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002665
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 29 Oct 2032 to 31 Dec 2030 (−22 months)
- 22 May 2026 registerMarked as Gate 1
- 30 Jan 2024 registerAdded to the register
Also at Kingsnorth 400kV Substation
Substation view3 other projects, 2.8 GW still to connect at this substation in total. 1.8 GW is due to connect here before this project’s connection date of 31 Dec 2030.