Cuxton 49.5MW BESS
Cuxton Energy Storage Limited at Kingsnorth 400kV Substation
- Connection date
- 31 May 2023
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 49.5 MW
- Connected now
- 0 MW
- Still to connect
- 49.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-002373
- In the register since
- September 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Nov 2023 registerConnection point changed from Kingsnorth 132kV Substation to Kingsnorth 400kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Kingsnorth 132kV to Kingsnorth 132kV Substation)
- 28 Oct 2022 registerConnection point changed from Kingsnorth 13kV to Kingsnorth 132kV
- 30 Sep 2022 registerAdded to the register
Also at Kingsnorth 400kV Substation
Substation view3 other projects, 2.8 GW still to connect at this substation in total.