Medway 3 Power Station
- Connection date
- 30 Apr 2032 +16 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + LAES (Liquid Air Energy Storage)
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002578
- In the register since
- May 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Dec 2030 to 30 Apr 2032 (+16 months)
- 31 Jul 2026 registerMarked as Gate 1
- 29 Jul 2025 registerTechnology changed from Gas (CCGT), Storage to Demand, LAES (Liquid Air Energy Storage)
- 28 Feb 2025 registerTechnology changed from Gas (OCGT) to Gas (CCGT), Storage
- 29 Oct 2024 registerConnection point changed from Grain 400kV Substation to Kingsnorth 400kV Substation
- 30 May 2023 registerAdded to the register
Also at Kingsnorth 400kV Substation
Substation view3 other projects, 2.8 GW still to connect at this substation in total. 2.3 GW is due to connect here before this project’s connection date of 30 Apr 2032.