MEDWAY POWER LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Medway Power Station | Grain 400kV Substation | Thermal (gas, biomass, waste) | 175 | 30 Oct 2028 | Not stated | Built |
| Medway 3 Power Station | Kingsnorth 400kV Substation | Storage | 500 | 30 Apr 2032 +16 mo | Gate 1 | Scoping |
Recent changes
- Medway 3 Power StationEngland and Wales, StorageConnection date moved from 31 Dec 2030 to 30 Apr 2032 (+16 months)+16 mo
- Medway 3 Power StationEngland and Wales, StorageMarked as Gate 1
- Medway 3 Power StationEngland and Wales, StorageTechnology changed from Gas (CCGT), Storage to Demand, LAES (Liquid Air Energy Storage)
- Medway 3 Power StationEngland and Wales, StorageTechnology changed from Gas (OCGT) to Gas (CCGT), Storage
- Medway 3 Power StationEngland and Wales, StorageConnection point changed from Grain 400kV Substation to Kingsnorth 400kV Substation
- Medway 3 Power StationEngland and Wales, StorageAdded to the registerNew
- Medway Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 30 Oct 2026 to 30 Oct 2028 (+24 months)+24 mo
- Medway Power StationEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Grain GSP to Grain 400kV Substation)
- Medway Power StationEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Grain to Grain GSP)
- Medway Power StationEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 0 MW to 175 MW
- Medway Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 30 Oct 2026
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?