Transmission / Projects / England and Wales
Connection date
Left 27 Aug 2024
Gate
Not stated
Status
Awaiting Consents
Technology
Storage + Solar
Total capacity
49.5 MW
Connected now
0 MW
Still to connect
49.5 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002068
In the register since
April 2023

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 27 Aug 2024 register
    Left the register (49.5 MW from 25 Oct 2024)
  • 30 May 2023 register
    Customer changed from YARE POWER LIMITED to ASH GREEN ENERGY FARM LIMITED
  • 28 Apr 2023 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO