Norwich Yare
- Connection date
- 18 Dec 2025
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 49.5 MW
- Connected now
- 0 MW
- Still to connect
- 49.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001076
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection date moved from 31 Oct 2024 to 18 Dec 2025 (+14 months)
- 28 Jun 2024 registerRenamed from Norwich
- 28 Jun 2024 registerTechnology changed from Gas (CCGT) to Storage, Solar
- 30 May 2023 registerCustomer changed from YARE POWER LIMITED to ASH GREEN ENERGY FARM LIMITED
- 30 May 2023 registerConnection date moved from 31 Oct 2023 to 31 Oct 2024 (+12 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Norwich to Norwich GSP)
- 31 May 2022 registerConnection date moved from 30 Jun 2024 to 31 Oct 2023 (−8 months)
- 30 Nov 2021 registerConnection date moved from 31 Oct 2023 to 30 Jun 2024 (+8 months)
- 29 Oct 2021 registerConnection date moved from 1 Jul 2022 to 31 Oct 2023 (+16 months)
- 26 Feb 2021 registerConnection date moved from 7 Jan 2022 to 1 Jul 2022 (+6 months)
Also at Norwich GSP
Substation viewNo other projects in the register at this connection point.