Saltholme
Grid supply point in North East (Northern Powergrid)
Northern Powergrid Embedded Capacity Register 1MW and Over, September 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Gas and other fossil | 10 | 425 MW | 275 MW | 150 MW |
| Storage | 1 | 101 MW | – | 101 MW |
| Bioenergy and waste | 2 | 54.1 MW | 54.1 MW | – |
| Other or not stated | 1 | 4.4 MW | 4.4 MW | – |
Storage capacity in MWh: no site here states any.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Seal Sands | 2 | 76 MW | 50 MW | ||||||||||||||||
2 sites, 126 MW: 76 MW connected, 50 MW accepted to connect
| |||||||||||||||||||
| Seal Sands | 1 | 61.8 MW | – | ||||||||||||||||
1 site, 61.8 MW: 61.8 MW connected
| |||||||||||||||||||
| Seal Sands | 1 | 4.4 MW | – | ||||||||||||||||
1 site, 4.4 MW: 4.4 MW connected
| |||||||||||||||||||
| Seal Sands | 1 | 4 MW | – | ||||||||||||||||
1 site, 4 MW: 4 MW connected
| |||||||||||||||||||
| Belasis Avenue BESS | 1 | – | 101 MW | ||||||||||||||||
1 site, 101 MW: 101 MW accepted to connect
| |||||||||||||||||||
| Port Clarence Gas | 1 | – | 100 MW | ||||||||||||||||
1 site, 100 MW: 100 MW accepted to connect
| |||||||||||||||||||
| Saltholme Gas North | 1 | 50 MW | – | ||||||||||||||||
1 site, 50 MW: 50 MW connected
| |||||||||||||||||||
| Saltholme Gas South | 1 | 50 MW | – | ||||||||||||||||
1 site, 50 MW: 50 MW connected
| |||||||||||||||||||
| Port Clarence Biomass | 1 | 49 MW | – | ||||||||||||||||
1 site, 49 MW: 49 MW connected
| |||||||||||||||||||
| Billingham Synthetic | 1 | 21.9 MW | – | ||||||||||||||||
1 site, 21.9 MW: 21.9 MW connected
| |||||||||||||||||||
| Greatham | 2 | 11.8 MW | – | ||||||||||||||||
2 sites, 11.8 MW: 11.8 MW connected
| |||||||||||||||||||
| North Bank | 1 | 4.3 MW | – | ||||||||||||||||
1 site, 4.3 MW: 4.3 MW connected
| |||||||||||||||||||
Not found in Northern Powergrid's September 2026 edition
1 site last found at this grid supply point was not found in this edition by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.
- Seal Sands HRS Biomass last found in the June 2026 edition
What changed recently
Changes to the sites here found in both of two consecutive monthly editions, the latest first.
August 2026 edition to September 2026 edition: 14 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.
No change to the status, capacity, technology or customer of the sites here in the editions of Northern Powergrid's register QueueWatch holds.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.