Belasis Avenue BESS
Belasis Avenue BESS at Saltholme
Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- Not published by Northern Powergrid
- Status
- Accepted to connect
- Planning consent
- Granted 19 Apr 2024
Stockton-on-Tees, reference 23/1634/FUL · Source: REPD - Customer
- Belasis Avenue BESS
- Site name
- Belasis Avenue BESS
- Address
- Land South side of Belasis Avenue, Belasis Avenue, Billingham, County Durham, TS23 1LQ
- Grid reference
- Easting 447554, northing 523011
- Licence area
- North East (Northern Powergrid)
- Grid supply point
- Saltholme
- Bulk supply point
- Belasis Avenue BESS
- Primary substation
- Belasis Avenue BESS Direct
- Connection voltage
- 132 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 100.92 MW registered
- Registered capacity
- 100.92 MW
- Change to maximum export capacity
- 100.92 MW
- Change to maximum import capacity
- Not stated
- Flexible connection
- Yes
- In a connection queue
- Not published by Northern Powergrid
- Date accepted
- 16 Nov 2022
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by Northern Powergrid
- Transmission reinforcement reference
- Not published by Northern Powergrid
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 9 Dec 2022
- Tracked since
- March 2026 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the March 2026 edition, across 9 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at Saltholme
GSP view13 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 584 MW: 333 MW connected, 251 MW accepted to connect.
- Port Clarance Hydrogen & GasPort Clarance Hydrogen & Gas, Gas and other fossil, Port Clarence Gas Direct primaryAccepted100 MW
- Phillips Petroleum Cogeneration Plant (Seal Sands)Phillips Petroleum Cogeneration Plant (Seal Sands), Gas and other fossil, Phillips Petroleum primaryConnected76 MW
- Viking Power StationViking Power Station, Gas and other fossil, Viking Power primaryConnected61.75 MW
- Conoco Phillips GasConoco Phillips Gas, Gas and other fossil, Phillips Petroleum primaryAccepted50 MW
- RSPB SaltholmeSaltholme Gas South, Gas and other fossil, Saltholme Gas South Direct primaryConnected49.95 MW
- RSPB SaltholmeSaltholme Gas North, Gas and other fossil, Saltholme Gas North Direct primaryConnected49.95 MW
- Teesside Renewable Energy Plant (Port Clarence Biomass)Teesside Renewable Energy Plant (Port Clarence Biomass), Bioenergy and waste, Port Clarence Biomass Direct primaryConnected49 MW
- Growhow UK Ltd (Billingham)Growhow UK Ltd (Billingham), Gas and other fossil, Billingham Synthetic Direct primaryConnected21.85 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.