Distribution / Sites / Customer

Wind Estate (UK) Ltd

Customer named in the DNOs’ registers

In SPEN’s September 2026 edition

The registers spell this customer’s name more than one way: “Wind Estate (UK) Ltd” (5 sites), “Wind Estate (UK) Limited” (2 sites) and “Wind Estate (UK) Ltd.” (1 site).

8sites of 1 MW and over
155 MWcapacity
–connected (0 sites)
155 MWaccepted to connect (8 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
SPENSeptember 2026 edition8155 MW–155 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Wind8155 MW–155 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
Gladsmuir Wind FarmSPENBathgateWindAccepted to connect31
Woodend Wind FarmSPENDrumcrossWindAccepted to connect25.2
Dunwan Dam Wind FarmSPENGiffnockWindAccepted to connect24.8
Pearie Law IISPENDrumcrossWindAccepted to connect22.24
Blackburn Wind FarmSPENEcclesWindAccepted to connect16.8
Garviland Wind FarmSPENGlenluceWindAccepted to connect13.5
Dewshill Wind FarmSPENNewarthillWindAccepted to connect12.6
Brownhill FarmSPENNewarthillWindAccepted to connect8.4

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
DrumcrossSPEN2–47.4 MW
BathgateSPEN1–31 MW
GiffnockSPEN1–24.8 MW
NewarthillSPEN2–21 MW
EcclesSPEN1–16.8 MW
GlenluceSPEN1–13.5 MW

What changed recently

Changes to its sites found in both editions of each pair, newest first.

SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 8 sites matched. Every August site and every September site had a match in the other edition.

  • Dewshill Wind FarmSPEN, September 2026 editionTarget energisation date moved from 3 Aug 2027 to 3 Sep 2027 (1 month later)
  • Gladsmuir Wind FarmSPEN, August 2026 editionCapacity changed from 43.4 MW to 31 MW
  • Gladsmuir Wind FarmSPEN, August 2026 editionExport capacity changed from 41.5 MW to 31 MW
  • Garviland Wind FarmSPEN, July 2026 editionCapacity changed from 24 MW to 13.5 MW
  • Garviland Wind FarmSPEN, July 2026 editionExport capacity changed from 21.3 MW to 12.5 MW
  • Blackburn Wind FarmSPEN, May 2026 editionCustomer stated as Wind Estate (UK) Ltd. (not stated in the April 2026 edition)
  • Dunwan Dam Wind FarmSPEN, May 2026 editionFlexible connection changed from “yes” to “no”
  • Dunwan Dam Wind FarmSPEN, May 2026 editionIn a connection queue changed from “yes” to “no”
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?