QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Lochcraigs Solar Park

Quintas Energy UK at Saltcoats A

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
31 Mar 2017
Status
Connected
Planning consent
Granted 13 Aug 2015
North Ayrshire, reference 15/00252/PP · Source: REPD
Customer
Quintas Energy UK
Site name
Lochcraigs Solar Park
Address
Lochcraig Farm, Lochcraig Farm, Stevenston, North Ayrshire, KA20 4LB
Grid reference
Easting 227855, northing 643749
Licence area
Central and Southern Scotland (SPD)
Grid supply point
Saltcoats A
Bulk supply point
Not stated
Primary substation
BYREHILL (11kV)
Connection voltage
11 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 4.75 MW registered
Registered capacity
4.75 MW
Maximum export capacity
4.75 MW
Maximum import capacity
0 MW
Flexible connection
No
In a connection queue
No
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
1800060893728
Import MPAN
1800060893719
Last updated
14 Jul 2020
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Saltcoats A

GSP view

6 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 114 MW: 71 MW connected, 43 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.