Distribution / SPEN / Grid supply point

Legacy

Grid supply point in Merseyside, Cheshire and North Wales (SPM)

SPEN Embedded Capacity Register >1MW, September 2026 edition

49sites of 1 MW and over
615 MWcapacity
328 MWconnected (40 sites)
287 MWaccepted to connect (9 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar22326 MW98 MW228 MW
Wind8171 MW126 MW45 MW
Gas and other fossil1096.9 MW88.6 MW8.3 MW
Bioenergy and waste815.5 MW15.5 MW–
Storage14.9 MW–4.9 MW

Storage capacity in MWh: not published by SPEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT1310.7 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT135.3 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT115 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT113.5 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT112.5 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT112.5 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT112.4 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT112.1 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT112 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT111.9 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT111.5 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT111.3 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT111.2 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT111 MW–
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT112157 MW19 MW
CARNO447.6 MW45 MW
BRYMBO GT1 / LEGACY LOCAL GT1 / MARCHWIEL GT1 / MARCHWIEL GT2 / WREXHAM GT121.8 MW4.9 MW
BRYMBO GT1 / LEGACY LOCAL GT1 / MARCHWIEL GT1 / MARCHWIEL GT2 / WREXHAM GT126.5 MW–
BRYMBO GT1 / LEGACY LOCAL GT1 / MARCHWIEL GT1 / MARCHWIEL GT2 / WREXHAM GT11–4.9 MW
BRYMBO GT1 / LEGACY LOCAL GT1 / MARCHWIEL GT1 / MARCHWIEL GT2 / WREXHAM GT112.2 MW–
BRYMBO GT1 / LEGACY LOCAL GT1 / MARCHWIEL GT1 / MARCHWIEL GT2 / WREXHAM GT111.4 MW–
BRYMBO GT1 / LEGACY LOCAL GT1 / MARCHWIEL GT1 / MARCHWIEL GT2 / WREXHAM GT1538.7 MW13.4 MW
Not stated330 MW200 MW

Search and filter all 49 sites at Legacy

Not found among the sites of 1 MW and over in SPEN’s September 2026 edition

2 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

August 2026 edition to September 2026 edition: 49 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.

  • KronospanAugust 2026 editionCustomer changed from River Island to Kronospan Limited
  • KronospanAugust 2026 editionExport capacity changed from 47.4 MW to 28 MW
  • KronospanAugust 2026 editionIn a connection queue changed from “yes” to “no”
  • KronospanAugust 2026 editionStatus changed from “accepted to connect” to “connected”
  • KronospanAugust 2026 editionTechnology changed from Solar to Gas and other fossil
  • Moor FarmAugust 2026 editionCustomer changed from SPF Moorfarm Ltd to G59 Projects
  • KronospanJuly 2026 editionCapacity changed from 47.4 MW to 28 MW
  • KronospanJuly 2026 editionTechnology changed from Gas and other fossil to Solar
  • Stanwardine Grange PV & BESSJuly 2026 editionTechnology changed from Storage to Solar
  • Williams Farm Solar (Phase 2)July 2026 editionCapacity changed from 16.27 MW to 10 MW
  • Williams Farm Solar (Phase 2)July 2026 editionCustomer changed from Renewabuild to Solar Ventures
  • Williams Farm Solar (Phase 2)July 2026 editionTechnology changed from Storage to Solar
  • Ash RoadJune 2026 editionCapacity changed from 5 MW to 4.9 MW
  • Ash RoadJune 2026 editionExport capacity changed from 5 MW to 4.9 MW
  • Bwlch Y CibauJune 2026 editionCapacity changed from 5 MW to 4.9 MW
  • Bwlch Y CibauJune 2026 editionExport capacity changed from 5 MW to 4.9 MW
  • KronospanJune 2026 editionCustomer changed from Kronospan Limited to River Island
  • KronospanJune 2026 editionIn a connection queue changed from “no” to “yes”
  • KronospanJune 2026 editionStatus changed from “connected” to “accepted to connect”
  • Stanwardine Grange PV & BESSJune 2026 editionTechnology changed from Solar to Storage
  • Bryn Plentyn FarmMay 2026 editionCustomer stated as Cr & Gm Woollam & Son (not stated in the April 2026 edition)
  • Solar 13 Ash Road SouthMay 2026 editionCustomer stated as Aniron Ltd (not stated in the April 2026 edition)
  • Wykey FarmMay 2026 editionCustomer stated as W H Gittins & Sons (not stated in the April 2026 edition)
  • KronospanApril 2026 editionCustomer changed from River Island to Kronospan Limited
  • KronospanApril 2026 editionIn a connection queue changed from “yes” to “no”
  • KronospanApril 2026 editionStatus changed from “accepted to connect” to “connected”
  • Moor FarmApril 2026 editionCustomer changed from G59 Projects to SPF Moorfarm Ltd
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.