Neilston 400kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Neilston Synchronous Compensation | NEILSTON GRID SERVICES LIMITED | Other | 0 | 12 Jun 2025 (0 MW) | Not stated | Consents Approved |
| Neilston 400kV Greener Grid Park | Statkraft UK Ltd | Storage | 600 | 31 Oct 2029 +29 mo | Gate 2 | Consents Approved |
| Hurlet Battery | P-FREQUENCY LTD | Storage | 400 | 31 Oct 2033 | Gate 1 | Scoping |
Recent changes
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageStatus changed from Awaiting Consents to Consents Approved
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageConnection date moved from 17 May 2027 to 31 Oct 2029 (+29 months)+29 mo
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Hurlet BatterySouth Scotland, StorageMarked as Gate 1
- Neilston Synchronous CompensationSouth Scotland, OtherConnection date moved from 31 Jul 2024 to 12 Jun 2025 (+10 months)+10 mo
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageStatus changed from Scoping to Awaiting Consents
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Storage
- Hurlet BatterySouth Scotland, StorageAdded to the registerNew
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageCapacity changed from 33 MW to 600 MW
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageConnection date moved from 31 Oct 2026 to 17 May 2027 (+7 months)+7 mo
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageSubstation name updated in the register (from Neilston 400kV to Neilston 400kV Substation)
- Neilston Synchronous CompensationSouth Scotland, OtherSubstation name updated in the register (from Neilston 400kV to Neilston 400kV Substation)
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageAdded to the registerNew
- Neilston Synchronous CompensationSouth Scotland, OtherCustomer changed from WP GRID SERVICES 9 LIMITED to NEILSTON GRID SERVICES LIMITED
- Neilston Synchronous CompensationSouth Scotland, OtherStatus changed from Scoping to Consents Approved
- Neilston Synchronous CompensationSouth Scotland, OtherAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?