Neilston 400kV Greener Grid Park
- Connection date
- 31 Oct 2029 +29 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001419
- In the register since
- June 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Awaiting Consents to Consents Approved
- 14 Aug 2026 registerConnection date moved from 17 May 2027 to 31 Oct 2029 (+29 months)
- 14 Aug 2026 registerGiven a Gate 2 connection offer
- 30 May 2025 registerStatus changed from Scoping to Awaiting Consents
- 30 May 2025 registerTechnology changed from Storage, Reactive compensation to Storage
- 28 Nov 2023 registerCapacity changed from 33 MW to 600 MW
- 31 Jan 2023 registerConnection date moved from 31 Oct 2026 to 17 May 2027 (+7 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Neilston 400kV to Neilston 400kV Substation)
- 30 Jun 2022 registerAdded to the register
Also at Neilston 400kV Substation
Substation view2 other projects, 1 GW still to connect at this substation in total.