Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Renewable Energy Systems Limited

Customer named in the TEC register

13projects in the register
3.6 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Clune Wind FarmClune 132/33 kV SubstationStorage with solar or wind18730 Apr 2030Gate 1Scoping
Killoch BESSKilloch BESS 132kV SubstationStorage15030 Sep 2030Gate 1Scoping
Bishops Dal Energy ParkBISHOPS DAL ENERGY PARK 132kV SUBSTATIONStorage15029 Oct 2030Gate 1Scoping
Aberarder Extension Wind FarmAberarder Extension Wind Farm 132/33kV SubstationStorage with solar or wind13830 Apr 2031Gate 1Scoping
Bloch Energy ParkBloch Energy Park 132kV SubstationStorage with solar or wind12631 Oct 2031Gate 1Scoping
CraigendArbroath GSPSolar49.930 Jun 2032Not statedScoping
Letch Beck Energy ParkNorton East 400kV SubstationStorage with solar or wind60031 Oct 2033Gate 1Scoping
Cliff Hill Energy FarmNavenby 400kV SubstationStorage with solar or wind80030 Oct 2034Gate 1Scoping
Fairgreen Energy StorageRayleigh Main 132kV SubstationStorage15031 Oct 2034Gate 1Scoping
Greengage FarmBiggleswade 400kV SubstationStorage with solar or wind50031 Oct 2034Gate 1Scoping
Killean Wind FarmCARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATIONOnshore wind6031 Oct 2034Gate 1Scoping
Blair Hill Wind FarmBLAIR HILL WIND FARM 132KV SUBSTATIONOnshore wind9931 Oct 2036Gate 1Scoping
Lower Pool Energy ParkDerbyshire Connection Node B 400kV SubstationStorage with solar or wind60030 Oct 2037 +84 moGate 1Scoping

Left the register since January 2021: Cairn Duhie Wind Farm (84 MW), Gleann Eoghainn (25 MW), Kintradwell Energy Park (71.4 MW), Red Hill Energy Park (800 MW), Paxton Dal Energy Park (600 MW), Lessnessock Solar Farm (150 MW), Glebe Energy Park (800 MW), Leys Energy Storage (400 MW), Acha Energy Storage (600 MW).

Recent changes

  • Cliff Hill Energy FarmEngland and Wales, Storage with solar or windCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
  • Letch Beck Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
  • Cliff Hill Energy FarmEngland and Wales, Storage with solar or windCustomer changed from Renewable Energy Systems Limited to CAIRN DUHIE ENERGY LIMITED
  • Letch Beck Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Renewable Energy Systems Limited to CAIRN DUHIE ENERGY LIMITED
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Renewable Energy Systems Limited to CAIRN DUHIE ENERGY LIMITED
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2030 to 30 Oct 2037 (+84 months)+84 mo
  • Killean Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from CARRADALE 3 GSP to CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION)
  • Killean Wind FarmNorth Scotland, Onshore windMarked as Gate 1
  • Blair Hill Wind FarmSouth Scotland, Onshore windConnection point changed from Craigenputtlock 400/132 kV Substation to BLAIR HILL WIND FARM 132KV SUBSTATION
  • Fairgreen Energy StorageEngland and Wales, StorageConnection point changed from Rayleigh Main GSP to Rayleigh Main 132kV Substation
  • Fairgreen Energy StorageEngland and Wales, StorageMarked as Gate 1
  • Blair Hill Wind FarmSouth Scotland, Onshore windMarked as Gate 1
  • Cliff Hill Energy FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Bishops Dal Energy ParkSouth Scotland, StorageMarked as Gate 1
  • Bloch Energy ParkSouth Scotland, Storage with solar or windMarked as Gate 1
  • Clune Wind FarmNorth Scotland, Storage with solar or windMarked as Gate 1
  • Aberarder Extension Wind FarmNorth Scotland, Storage with solar or windConnection point changed from Aberarder Wind Farm 132/33kV Substation to Aberarder Extension Wind Farm 132/33kV Substation
  • Aberarder Extension Wind FarmNorth Scotland, Storage with solar or windMarked as Gate 1
  • Bishops Dal Energy ParkSouth Scotland, StorageConnection point changed from Eccles 132/33kV to BISHOPS DAL ENERGY PARK 132kV SUBSTATION
  • Greengage FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Killoch BESSSouth Scotland, StorageConnection point changed from Killoch BESS 275kV substation to Killoch BESS 132kV Substation
  • Killoch BESSSouth Scotland, StorageMarked as Gate 1
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windMarked as Gate 1
  • Letch Beck Energy ParkEngland and Wales, Storage with solar or windMarked as Gate 1
  • Cliff Hill Energy FarmEngland and Wales, Storage with solar or windCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
  • Letch Beck Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
  • Blair Hill Wind FarmSouth Scotland, Onshore windConnection point changed from Glenlee 132/11kV to Craigenputtlock 400/132 kV Substation
  • Aberarder Extension Wind FarmNorth Scotland, Storage with solar or windConnection point changed from Tomatin 275/132 kV Substation to Aberarder Wind Farm 132/33kV Substation
  • Cliff Hill Energy FarmEngland and Wales, Storage with solar or windCustomer changed from Renewable Energy Systems Limited to Cairn Duhie Energy Limited
  • Letch Beck Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Renewable Energy Systems Limited to Cairn Duhie Energy Limited
  • Letch Beck Energy ParkEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Renewable Energy Systems Limited to Cairn Duhie Energy Limited
  • Bishops Dal Energy ParkSouth Scotland, StorageConnection point changed from Bishop Dal 132kV Substation to Eccles 132/33kV
  • Bishops Dal Energy ParkSouth Scotland, StorageConnection date moved from 31 Jul 2030 to 29 Oct 2030 (+3 months)+3 mo
  • Bishops Dal Energy ParkSouth Scotland, StorageTechnology changed from Storage, Solar to Storage
  • Fairgreen Energy StorageEngland and Wales, StorageAdded to the registerNew
  • Killean Wind FarmNorth Scotland, Onshore windAdded to the registerNew
  • Acha Energy StorageNorth Scotland, StorageLeft the register (600 MW from 31 Oct 2033)600 MW
  • Blair Hill Wind FarmSouth Scotland, Onshore windAdded to the registerNew
  • Clune Wind FarmNorth Scotland, Storage with solar or windCapacity changed from 150 MW to 187 MW
  • Clune Wind FarmNorth Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
  • Killoch BESSSouth Scotland, StorageConnection point changed from Killoch BESS 132kV Substation to Killoch BESS 275kV substation
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windConnection point changed from Earl Shilton 400kV Substation to Derbyshire Connection Node B 400kV Substation
  • Leys Energy StorageNorth Scotland, StorageLeft the register (400 MW from 31 Oct 2032)400 MW
  • Killoch BESSSouth Scotland, StorageConnection point changed from Killoch BESS 275kV substation to Killoch BESS 132kV Substation
  • Red Hill Energy ParkEngland and Wales, Storage with solar or windLeft the register (800 MW from 24 Oct 2035)800 MW
  • Glebe Energy ParkEngland and Wales, Storage with solar or windLeft the register (800 MW from 31 Oct 2032)800 MW
  • CraigendNorth Scotland, SolarAdded to the registerNew
  • Paxton Dal Energy ParkSouth Scotland, Storage with solar or windLeft the register (600 MW from 31 Jul 2030)600 MW
  • Clune Wind FarmNorth Scotland, Storage with solar or windTransmission owner changed from SPT to SHET
  • Lessnessock Solar FarmSouth Scotland, SolarLeft the register (150 MW from 30 Jul 2030)150 MW
  • Greengage FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Lower Pool Energy ParkEngland and Wales, Storage with solar or windConnection point changed from Earl Shilton 275kV to Earl Shilton 400kV Substation
  • Kintradwell Energy ParkNorth Scotland, Onshore windLeft the register (71.4 MW from 30 Jun 2027)71.4 MW
  • Bloch Energy ParkSouth Scotland, Storage with solar or windSubstation name updated in the register (from Bloch Energy Park to Bloch Energy Park 132kV substation)
  • Clune Wind FarmNorth Scotland, Storage with solar or windTransmission owner changed from SHET to SPT
  • Killoch BESSSouth Scotland, StorageAdded to the registerNew
  • Acha Energy StorageNorth Scotland, StorageAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO