Aberarder Extension Wind Farm
Renewable Energy Systems Limited at Aberarder Extension Wind Farm 132/33kV Substation
- Connection date
- 30 Apr 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 138 MW
- Connected now
- 0 MW
- Still to connect
- 138 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002589
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Apr 2026 registerConnection point changed from Aberarder Wind Farm 132/33kV Substation to Aberarder Extension Wind Farm 132/33kV Substation
- 7 Apr 2026 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Tomatin 275/132 kV Substation to Aberarder Wind Farm 132/33kV Substation
- 31 Oct 2023 registerAdded to the register
Also at Aberarder Extension Wind Farm 132/33kV Substation
Substation viewNo other projects in the register at this connection point.