Transmission / Projects / North Scotland

Millennium South

RENANTIS UK LIMITED at Millennium South 132/33kV Substation

Connection date
Left 31 Oct 2023
Gate
Not stated
Status
Consents Approved
Technology
Onshore wind
Total capacity
25 MW
Connected now
0 MW
Still to connect
25 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Directly Connected
Region
North Scotland
Project number
PRO-000311
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 31 Oct 2023 register
    Left the register (25 MW from 31 Oct 2021)
  • 31 Jan 2023 register
    Customer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED

Also at Millennium South 132/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO