Gleann Eoghainn
Renantis UK Limited at Dunvegan 132/33kV Grid Supply Point Substation
- Connection date
- 30 Nov 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 25 MW
- Connected now
- 0 MW
- Still to connect
- 25 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001275
- In the register since
- March 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerConnection point changed from Edinbane 132/33kV Substation to Dunvegan 132/33kV Grid Supply Point Substation
- 27 Jun 2025 registerConnection point changed from Dunvegan GSP to Edinbane 132/33kV Substation
- 27 Jun 2025 registerConnection date moved from 31 Oct 2027 to 30 Nov 2029 (+25 months)
- 28 Mar 2025 registerCustomer changed from Nadara Limited to Renantis UK Limited
- 28 Mar 2025 registerConnection point changed from Edinbane 132/33kV Substation to Dunvegan GSP
- 28 Feb 2025 registerCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- 27 Feb 2024 registerConnection point changed from Dunvegan GSP to Edinbane 132/33kV Substation
- 31 Mar 2023 registerAdded to the register
Also at Dunvegan 132/33kV Grid Supply Point Substation
Substation viewNo other projects in the register at this connection point.