Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Assel Valley Extension Wind Farm

Renantis UK Limited at Maybole GSP

Connection date
31 Oct 2032
Gate
Gate 1
Status
Scoping
Technology
Storage + Onshore wind
Total capacity
175 MW
Connected now
0 MW
Still to connect
175 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-002632
In the register since
October 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
10888831 Oct 2032Gate 1Scoping
208717530 Oct 2037Gate 1Scoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 19 Dec 2025 register
    Stage 1: Marked as Gate 1
  • 19 Dec 2025 register
    Stage 2: Marked as Gate 1
  • 28 Mar 2025 register
    Customer changed from Nadara Limited to Renantis UK Limited
  • 28 Feb 2025 register
    Customer changed from RENANTIS UK LIMITED to Nadara Limited
  • 24 Dec 2024 register
    Stage 1: Connection date moved from 30 Oct 2032 to 31 Oct 2032 (1 day later)
  • 30 Jul 2024 register
    Restructured from 1 stage (88 MW from 30 Oct 2030) to 2 stages (88 MW from 30 Oct 2032, 87 MW from 30 Oct 2037). First connection date +24 months
  • 31 Oct 2023 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO