Teeside Connection Node A 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Lackenby PV & BESS Station | IB VOGT UK LTD | Storage with solar or wind | 240 | 31 Oct 2033 | Gate 1 | Scoping |
| NatPower Teesside Green Energy Park | Old Rides Energy Storage Limited | Storage | 1,000 | 31 Oct 2035 | Not stated | Consents Approved |
Recent changes
- Lackenby PV & BESS StationEngland and Wales, Storage with solar or windConnection point changed from Lackenby 275kV Substation to Teeside Connection Node A 400kV Substation
- Lackenby PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- NatPower Teesside Green Energy ParkEngland and Wales, StorageCustomer changed from NP SPV 27 Limited to Old Rides Energy Storage Limited
- NatPower Teesside Green Energy ParkEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- NatPower Teesside Green Energy ParkEngland and Wales, StorageCustomer changed from NATPOWER MARINE LIMITED to NP SPV 27 Limited
- NatPower Teesside Green Energy ParkEngland and Wales, StorageConnection point changed from Lackenby 400kV Substation to Teeside Connection Node A 400kV Substation
- NatPower Teesside Green Energy ParkEngland and Wales, StorageCapacity changed from 1,034 MW to 1,000 MW
- NatPower Teesside Green Energy ParkEngland and Wales, StorageCapacity changed from 1,000 MW to 1,034 MW
- Lackenby PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- NatPower Teesside Green Energy ParkEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?