Ashbrook Lane BESS
Downing Renewable Developments LLP at WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION
- Connection date
- 31 Oct 2034 +36 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 250 MW
- Connected now
- 0 MW
- Still to connect
- 250 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003534
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)
- 10 Oct 2026 registerMarked as Gate 1
- 14 Apr 2026 registerConnection point changed from Wymondley GSP to WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION
- 30 Jan 2024 registerAdded to the register
Also at WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION
Substation view1 other project, 1.2 GW still to connect at this substation in total. 1 GW is due to connect here before this project’s connection date of 31 Oct 2034.