Caegarw Farm
Downing Renewable Developments LLP at Margam B 400kV Substation
- Connection date
- 10 May 2037 +2 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 350 MW
- Connected now
- 0 MW
- Still to connect
- 350 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002605
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 10 Mar 2037 to 10 May 2037 (+2 months)
- 1 May 2026 registerMarked as Gate 1
- 14 Apr 2026 registerConnection point changed from Pyle 275kV Substation to Margam B 400kV Substation
- 29 Jul 2025 registerConnection date moved from 10 May 2037 to 10 Mar 2037 (−2 months)
- 29 Sep 2023 registerAdded to the register
Also at Margam B 400kV Substation
Substation viewNo other projects in the register at this connection point.