Leeds North Connection Node C 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH) | TELIS ENERGY UK LIMITED | Multi-technology hub | 1,000 | 30 Oct 2035 | Gate 1 | Scoping |
| FCC Thurcroft BESS | Downing Renewable Developments LLP | Storage | 750 | 30 Oct 2035 +24 mo | Gate 1 | Scoping |
| NEL Bluebell | SFEL Bluebell Limited | Storage | 240 | 30 Oct 2035 | Not stated | Scoping |
| NEL Springfield | UE 3 LTD | Storage | 240 | 30 Oct 2035 | Not stated | Scoping |
| West Melton PV & BESS Station | IBV WEST MELTON SOLAR PARK LIMITED | Storage with solar or wind | 200 | 30 Oct 2035 +24 mo | Gate 1 | Scoping |
Recent changes
- FCC Thurcroft BESSEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- FCC Thurcroft BESSEngland and Wales, StorageConnection date moved from 30 Oct 2035 to 31 Oct 2033 (−24 months)−24 mo
- FCC Thurcroft BESSEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- West Melton PV & BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- FCC Thurcroft BESSEngland and Wales, StorageConnection point changed from Thorpe Marsh GSP to Leeds North Connection Node C 400kV Substation
- FCC Thurcroft BESSEngland and Wales, StorageMarked as Gate 1
- NEL SpringfieldEngland and Wales, StorageCustomer changed from Newton Energi Limited to UE 3 LTD
- West Melton PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)England and Wales, Multi-technology hubConnection point changed from Brodsworth 400kV Substation to Leeds North Connection Node C 400kV Substation
- Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)England and Wales, Multi-technology hubMarked as Gate 1
- NEL SpringfieldEngland and Wales, StorageConnection point changed from Ferrybridge B GSP to Leeds North Connection Node C 400kV Substation
- NEL BluebellEngland and Wales, StorageCustomer changed from Newton Energi Limited to SFEL Bluebell Limited
- West Melton PV & BESS StationEngland and Wales, Storage with solar or windCustomer changed from IB VOGT UK LTD to IBV WEST MELTON SOLAR PARK LIMITED
- Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)England and Wales, Multi-technology hubAdded to the registerNew
- West Melton PV & BESS StationEngland and Wales, Storage with solar or windConnection point changed from West Melton 275kV Substation to Leeds North Connection Node C 400kV Substation
- NEL BluebellEngland and Wales, StorageConnection point changed from Ferrybridge B GSP to Leeds North Connection Node C 400kV Substation
- NEL BluebellEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- NEL SpringfieldEngland and Wales, StorageConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
- FCC Thurcroft BESSEngland and Wales, StorageAdded to the registerNew
- West Melton PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- NEL BluebellEngland and Wales, StorageAdded to the registerNew
- NEL SpringfieldEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?