Bluestone Energy Ltd
Customer named in the TEC register
Projects
Left the register since January 2021: Scottish Water Airdrie STW 60MW BESS (45 MW), Cathkin Quarry BESS (60 MW), Summerston PV 50MW (50 MW), Malcolmwood Farm BESS (60 MW).
Recent changes
- Drakelow Power Station 3 BESSEngland and Wales, StorageStatus changed from Under Construction/Commissioning to Scoping
- Scottish Water Bonnybridge STW 60MW BESSSouth Scotland, StorageConnection date moved from 31 Jul 2030 to 31 Oct 2030 (+3 months)+3 mo
- Dougliehill BESSSouth Scotland, StorageMarked as Gate 1
- Scottish Water Bonnybridge STW 60MW BESSSouth Scotland, StorageConnection point changed from Bonnybridge 275/33kV Substation to Bonnybridge 132/33kV
- SEC 1 BESSSouth Scotland, StorageSubstation name updated in the register (from Finnieston 132/33kV Substation to Finnieston GSP)
- SEC 1 BESSSouth Scotland, StorageMarked as Gate 1
- Scottish Water Bonnybridge STW 60MW BESSSouth Scotland, StorageMarked as Gate 1
- Scottish Water Laigh Park STWSouth Scotland, StorageMarked as Gate 1
- Middleton Farm BESSSouth Scotland, StorageConnection point changed from Neilston 400kV Substation to MIDDLETON FARM 400KV SUBSTATION
- Dougliehill BESSSouth Scotland, StorageSubstation name updated in the register (from Devol Moor 132/33kV to DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION)
- Grovers Farm BESSEngland and Wales, StorageMarked as Gate 1
- Upper College Farm BESSEngland and Wales, StorageTransmission owner changed from SHET to NGET
- Beddington 2 BESSEngland and Wales, StorageConnection point changed from Beddington 132kV Substation to London South Connection Node A 132kV Substation
- Beddington 2 BESSEngland and Wales, StorageMarked as Gate 1
- CRT Keadby 2England and Wales, StorageConnection point changed from Keadby GSP to Trent Valley North Connection Node B 132kV Substation
- CRT Keadby 2England and Wales, StorageMarked as Gate 1
- Drakelow Power Station 1 BESSEngland and Wales, StorageConnection point changed from Drakelow GSP to DERBYSHIRE CONNECTION NODE E 132KV SUBSTATION
- Drakelow Power Station 1 BESSEngland and Wales, StorageMarked as Gate 1
- Drakelow Power Station 2 BESSEngland and Wales, StorageConnection point changed from Drakelow GSP to DERBYSHIRE CONNECTION NODE E 132 KV SUBSTATION
- Drakelow Power Station 2 BESSEngland and Wales, StorageMarked as Gate 1
- Drakelow Power Station 3 BESSEngland and Wales, StorageConnection point changed from Drakelow GSP to ERBYSHIRE CONNECTION NODE E 132kV SUBSTATION
- Drakelow Power Station 3 BESSEngland and Wales, StorageMarked as Gate 1
- Drakelow Power Station 4England and Wales, StorageConnection point changed from Drakelow GSP to DERBYSHIRE CONNECTION NODE E 132 KV SUBSTATION
- Drakelow Power Station 4England and Wales, StorageMarked as Gate 1
- St. Marys Lane - Upminster BESSEngland and Wales, StorageConnection point changed from Warley GSP to Warley 132kV Substation
- St. Marys Lane - Upminster BESSEngland and Wales, StorageMarked as Gate 1
- Upminster Warley 3England and Wales, StorageConnection point changed from Warley GSP to Warley 132kV Substation
- Upminster Warley 3England and Wales, StorageMarked as Gate 1
- Upper College Farm BESSEngland and Wales, StorageTransmission owner changed from NGET to SHET
- Upper College Farm BESSEngland and Wales, StorageMarked as Gate 1
- SEC 1 BESSSouth Scotland, StorageSubstation name updated in the register (from Finnieston GSP to Finnieston 132/33kV Substation)
- High Bardrain Wood & MoorSouth Scotland, StorageMarked as Gate 1
- Upper College Farm BESSEngland and Wales, StorageConnection point changed from Hurst GSP to NORTH KENT CONNECTION NODE C 132KV SUBSTATION
- Lacey's Farm BESSEngland and Wales, StorageMarked as Gate 1
- Middleton Farm BESSSouth Scotland, StorageMarked as Gate 1
- High Bardrain Wood & MoorSouth Scotland, StorageConnection point changed from Neilston 400kV Substation to HIGH BARDRAIN WOOD & MOOR 132KV SUBSTATION
- Scottish Water Bonnybridge STW 60MW BESSSouth Scotland, StorageConnection date moved from 31 Oct 2030 to 31 Jul 2030 (−3 months)−3 mo
- High Bardrain Wood & MoorSouth Scotland, StorageAdded to the registerNew
- Scottish Water Airdrie STW 60MW BESSSouth Scotland, StorageLeft the register (45 MW from 31 Oct 2028)45 MW
- Summerston PV 50MWSouth Scotland, SolarLeft the register (50 MW from 30 Jun 2031)50 MW
- Malcolmwood Farm BESSSouth Scotland, StorageLeft the register (60 MW from 3 Jul 2026)60 MW
- St. Marys Lane - Upminster BESSEngland and Wales, StorageConnection date moved from 31 Oct 2030 to 31 Oct 2036 (+72 months)+72 mo
- CRT Keadby 2England and Wales, StorageAdded to the registerNew
- Drakelow Power Station 4England and Wales, StorageAdded to the registerNew
- Stanley Water WTW BESSSouth Scotland, StorageSubstation name updated in the register (from Paisley 132kV Substation to Paisley GSP)
- Stanley Water WTW BESSSouth Scotland, StorageConnection date moved from 30 Jun 2025 to 1 Oct 2028 (+39 months)+39 mo
- Upminster Warley 3England and Wales, StorageAdded to the registerNew
- Upper College Farm BESSEngland and Wales, StorageAdded to the registerNew
- Scottish Water Laigh Park STWSouth Scotland, StorageAdded to the registerNew
- Dougliehill BESSSouth Scotland, StorageConnection date moved from 30 Oct 2026 to 31 Oct 2026 (1 day later)
- Drakelow Power Station 2 BESSEngland and Wales, StorageAdded to the registerNew
- Drakelow Power Station 3 BESSEngland and Wales, StorageStatus changed from Built to Under Construction/Commissioning
- RAF Newton PV solarEngland and Wales, SolarConnection date moved from 31 Oct 2032 to 30 Oct 2034 (+24 months)+24 mo
- SEC 1 BESSSouth Scotland, StorageSubstation name updated in the register (from Finnieston 132/33kV to Finnieston GSP)
- Beddington 2 BESSEngland and Wales, StorageConnection date moved from 31 Oct 2028 to 31 Oct 2037 (+108 months)+108 mo
- Drakelow Power Station 3 BESSEngland and Wales, StorageAdded to the registerNew
- Grovers Farm BESSEngland and Wales, StorageConnection point changed from West Weybridge GSP to West London Connection Node B 132kV substation
- Scottish Water Bonnybridge STW 60MW BESSSouth Scotland, StorageAdded to the registerNew
- Dougliehill BESSSouth Scotland, StorageConnection point changed from Devol Moor 400/132/33kV to Devol Moor 132/33kV
- Lacey's Farm BESSEngland and Wales, StorageConnection point changed from Rayleigh Main 400kV Substation to South Anglia Connection Node C 400kV Substation
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?