Lacey's Farm BESS
Bluestone Energy Ltd at South Anglia Connection Node C 400kV Substation
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 924 MW
- Connected now
- 0 MW
- Still to connect
- 924 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004095
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Apr 2026 registerMarked as Gate 1
- 29 Oct 2024 registerConnection point changed from Rayleigh Main 400kV Substation to South Anglia Connection Node C 400kV Substation
- 29 Dec 2023 registerAdded to the register
Also at South Anglia Connection Node C 400kV Substation
Substation view4 other projects, 4.9 GW still to connect at this substation in total. 200 MW is due to connect here before this project’s connection date of 31 Oct 2033.
- Rat Hall Mod AppKingsway Solar Farm Limited, Storage with solar or wind, Gate 1Oct 2032700 MW
- CorytonCoryton 10 Renewables Limited, Solar, Gate 1Oct 20341 GW
- NatPower Tilbury Green Energy ParkNATPOWER MARINE UK LIMITED, Storage, Gate 1Oct 20341 GW
- Cold NortonBSR APPLICATIONS LIMITED, Storage with solar or wind, Gate 1Oct 20361.3 GW