Dougliehill BESS
Bluestone Energy Ltd at DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION
- Connection date
- 31 Oct 2026
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Granted 6 Aug 2025
Inverclyde, reference 25/0033/IC · Source: REPD - Technology
- Storage
- Total capacity
- 49 MW
- Connected now
- 0 MW
- Still to connect
- 49 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002411
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Sep 2026 registerMarked as Gate 1
- 24 Jul 2026 registerSubstation name updated in the register (from Devol Moor 132/33kV to DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION)
- 28 Mar 2025 registerConnection date moved from 30 Oct 2026 to 31 Oct 2026 (1 day later)
- 29 Oct 2024 registerConnection point changed from Devol Moor 400/132/33kV to Devol Moor 132/33kV
- 27 Sep 2024 registerConnection point changed from Devol Moor (SPD) GSP to Devol Moor 400/132/33kV
- 28 Jun 2024 registerRenamed from Scottish Water Dougliehill WPS
- 28 Jun 2024 registerConnection point changed from Devol Moor 132kV Substation to Devol Moor (SPD) GSP
- 29 Sep 2023 registerAdded to the register
Also at DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION
Substation viewNo other projects in the register at this connection point.