Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

South Anglia Connection Node C 400kV Substation

England and Wales, National Grid Electricity Transmission

5projects in the register
4.9 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Rat Hall Mod AppKingsway Solar Farm LimitedStorage with solar or wind70031 Oct 2032Gate 1Scoping
Lacey's Farm BESSBluestone Energy LtdStorage92431 Oct 2033Gate 1Scoping
CorytonCoryton 10 Renewables LimitedSolar1,00031 Oct 2034Gate 1Scoping
NatPower Tilbury Green Energy ParkNATPOWER MARINE UK LIMITEDStorage1,00031 Oct 2034Gate 1Scoping
Cold NortonBSR APPLICATIONS LIMITEDStorage with solar or wind1,25031 Oct 2036Gate 1Scoping

Recent changes

  • Rat Hall Mod AppEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Oct 2032 to 31 Oct 2032 (1 day later)
  • Rat Hall Mod AppEngland and Wales, Storage with solar or windStage 1: Marked as Gate 1
  • Rat Hall Mod AppEngland and Wales, Storage with solar or windConnection point changed from Burwell South 400kV Substation to South Anglia Connection Node C 400kV Substation
  • Rat Hall Mod AppEngland and Wales, Storage with solar or windStage 2: Marked as Gate 1
  • Rat Hall Mod AppEngland and Wales, Storage with solar or windCustomer changed from Downing Renewable Developments LLP to Kingsway Solar Farm Limited
  • Lacey's Farm BESSEngland and Wales, StorageMarked as Gate 1
  • CorytonEngland and Wales, SolarConnection point changed from Coryton South 400kV Substation to South Anglia Connection Node C 400kV Substation
  • CorytonEngland and Wales, SolarMarked as Gate 1
  • Cold NortonEngland and Wales, Storage with solar or windMarked as Gate 1
  • NatPower Tilbury Green Energy ParkEngland and Wales, StorageMarked as Gate 1
  • Rat Hall Mod AppEngland and Wales, Storage with solar or windRestructured from 1 stage (500 MW from 31 Oct 2032) to 2 stages (200 MW from 30 Oct 2032, 500 MW from 31 Oct 2034)
  • Cold NortonEngland and Wales, Storage with solar or windConnection point changed from Rayleigh 400kV Substation to South Anglia Connection Node C 400kV Substation
  • Cold NortonEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 31 Oct 2036 (+36 months)+36 mo
  • CorytonEngland and Wales, SolarConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)+36 mo
  • NatPower Tilbury Green Energy ParkEngland and Wales, StorageConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
  • NatPower Tilbury Green Energy ParkEngland and Wales, StorageAdded to the registerNew
  • CorytonEngland and Wales, SolarTechnology changed from Demand, Storage, Solar to Demand, Solar
  • Lacey's Farm BESSEngland and Wales, StorageConnection point changed from Rayleigh Main 400kV Substation to South Anglia Connection Node C 400kV Substation
  • Rat Hall Mod AppEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2036 to 31 Oct 2032 (−48 months)−48 mo
  • CorytonEngland and Wales, SolarCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Coryton 10 Renewables Limited
  • CorytonEngland and Wales, SolarTechnology changed from Demand, Solar to Demand, Storage, Solar
  • Rat Hall Mod AppEngland and Wales, Storage with solar or windAdded to the registerNew
  • Cold NortonEngland and Wales, Storage with solar or windAdded to the registerNew
  • Lacey's Farm BESSEngland and Wales, StorageAdded to the registerNew
  • CorytonEngland and Wales, SolarAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO