South Anglia Connection Node C 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Rat Hall Mod App | Kingsway Solar Farm Limited | Storage with solar or wind | 700 | 31 Oct 2032 | Gate 1 | Scoping |
| Lacey's Farm BESS | Bluestone Energy Ltd | Storage | 924 | 31 Oct 2033 | Gate 1 | Scoping |
| Coryton | Coryton 10 Renewables Limited | Solar | 1,000 | 31 Oct 2034 | Gate 1 | Scoping |
| NatPower Tilbury Green Energy Park | NATPOWER MARINE UK LIMITED | Storage | 1,000 | 31 Oct 2034 | Gate 1 | Scoping |
| Cold Norton | BSR APPLICATIONS LIMITED | Storage with solar or wind | 1,250 | 31 Oct 2036 | Gate 1 | Scoping |
Recent changes
- Rat Hall Mod AppEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Oct 2032 to 31 Oct 2032 (1 day later)
- Rat Hall Mod AppEngland and Wales, Storage with solar or windStage 1: Marked as Gate 1
- Rat Hall Mod AppEngland and Wales, Storage with solar or windConnection point changed from Burwell South 400kV Substation to South Anglia Connection Node C 400kV Substation
- Rat Hall Mod AppEngland and Wales, Storage with solar or windStage 2: Marked as Gate 1
- Rat Hall Mod AppEngland and Wales, Storage with solar or windCustomer changed from Downing Renewable Developments LLP to Kingsway Solar Farm Limited
- Lacey's Farm BESSEngland and Wales, StorageMarked as Gate 1
- CorytonEngland and Wales, SolarConnection point changed from Coryton South 400kV Substation to South Anglia Connection Node C 400kV Substation
- CorytonEngland and Wales, SolarMarked as Gate 1
- Cold NortonEngland and Wales, Storage with solar or windMarked as Gate 1
- NatPower Tilbury Green Energy ParkEngland and Wales, StorageMarked as Gate 1
- Rat Hall Mod AppEngland and Wales, Storage with solar or windRestructured from 1 stage (500 MW from 31 Oct 2032) to 2 stages (200 MW from 30 Oct 2032, 500 MW from 31 Oct 2034)
- Cold NortonEngland and Wales, Storage with solar or windConnection point changed from Rayleigh 400kV Substation to South Anglia Connection Node C 400kV Substation
- Cold NortonEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 31 Oct 2036 (+36 months)+36 mo
- CorytonEngland and Wales, SolarConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)+36 mo
- NatPower Tilbury Green Energy ParkEngland and Wales, StorageConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
- NatPower Tilbury Green Energy ParkEngland and Wales, StorageAdded to the registerNew
- CorytonEngland and Wales, SolarTechnology changed from Demand, Storage, Solar to Demand, Solar
- Lacey's Farm BESSEngland and Wales, StorageConnection point changed from Rayleigh Main 400kV Substation to South Anglia Connection Node C 400kV Substation
- Rat Hall Mod AppEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2036 to 31 Oct 2032 (−48 months)−48 mo
- CorytonEngland and Wales, SolarCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Coryton 10 Renewables Limited
- CorytonEngland and Wales, SolarTechnology changed from Demand, Solar to Demand, Storage, Solar
- Rat Hall Mod AppEngland and Wales, Storage with solar or windAdded to the registerNew
- Cold NortonEngland and Wales, Storage with solar or windAdded to the registerNew
- Lacey's Farm BESSEngland and Wales, StorageAdded to the registerNew
- CorytonEngland and Wales, SolarAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose