DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Dougliehill BESS | Bluestone Energy Ltd | Storage | 49 | 31 Oct 2026 Past date | Gate 1 | Scoping |
Recent changes
- Dougliehill BESSSouth Scotland, StorageMarked as Gate 1
- Dougliehill BESSSouth Scotland, StorageSubstation name updated in the register (from Devol Moor 132/33kV to DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION)
- Dougliehill BESSSouth Scotland, StorageConnection date moved from 30 Oct 2026 to 31 Oct 2026 (1 day later)
- Dougliehill BESSSouth Scotland, StorageConnection point changed from Devol Moor 400/132/33kV to Devol Moor 132/33kV
- Dougliehill BESSSouth Scotland, StorageConnection point changed from Devol Moor (SPD) GSP to Devol Moor 400/132/33kV
- Dougliehill BESSSouth Scotland, StorageRenamed from Scottish Water Dougliehill WPS
- Dougliehill BESSSouth Scotland, StorageConnection point changed from Devol Moor 132kV Substation to Devol Moor (SPD) GSP
- Dougliehill BESSSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?