Willington 400kV Substation
England and Wales, National Grid Electricity Transmission
3projects in the register
2.1 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Willington Energy Park | BROCKWELL STORAGE & SOLAR LIMITED | Storage with solar or wind | 500 | 30 Mar 2028 | Not stated | Scoping |
| Willington Green Energy Centre | WILLINGTON NG LIMITED | Storage with solar or wind | 1,025 | 30 Oct 2028 | Not stated | Scoping |
| Willington | SSE UTILITY SOLUTIONS LIMITED | Storage with solar or wind | 600 | 30 Oct 2029 | Gate 1 | Scoping |
Recent changes
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Capacity changed from 1,025 MW to 400 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Capacity changed from 0 MW to 625 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2037)
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Capacity changed from 400 MW to 1,025 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Capacity changed from 625 MW to 0 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2037)
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose