WILLINGTON NG LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Willington Green Energy Centre | Willington 400kV Substation | Storage with solar or wind | 1,025 | 30 Oct 2028 | Not stated | Scoping |
Recent changes
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Capacity changed from 1,025 MW to 400 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Capacity changed from 0 MW to 625 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2037)
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Capacity changed from 400 MW to 1,025 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Capacity changed from 625 MW to 0 MW
- Willington Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2037)
- Willington Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from WILLINGTON GREEN ENERGY LIMITED to WILLINGTON NG LIMITED
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Demand, Storage, Solar
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Demand, Storage, Solar
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Oct 2026 to 30 Oct 2028 (+24 months)+24 mo
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar, Reactive compensation to Storage, Solar
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Connection date moved from 30 Oct 2029 to 30 Oct 2031 (+24 months)+24 mo
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar, Reactive compensation to Storage, Solar
- Willington Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from WILLINGTON NG LIMITED to WILLINGTON GREEN ENERGY LIMITED
- Willington Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from WILLINGTON GREEN ENERGY LIMITED to WILLINGTON NG LIMITED
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Storage, Solar, Reactive compensation
- Willington Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Storage, Solar, Reactive compensation
- Willington Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (625 MW from 30 Oct 2029)
- Willington Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?