Willington Energy Park
BROCKWELL STORAGE & SOLAR LIMITED at Willington 400kV Substation
- Connection date
- 31 Oct 2028 +7 months since 9 Dec
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001964
- In the register since
- April 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Sep 2026 registerConnection date moved from 30 Mar 2028 to 31 Oct 2028 (+7 months)
- 28 Jun 2024 registerCustomer changed from RNA-ENERGY LTD to BROCKWELL STORAGE & SOLAR LIMITED
- 29 Apr 2022 registerAdded to the register
Also at Willington 400kV Substation
Substation view2 other projects, 2.1 GW still to connect at this substation in total. 400 MW is due to connect here before this project’s connection date of 31 Oct 2028.