New Deer 400kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Green Volt Offshore Windfarm | Green Volt Offshore Windfarm Ltd | Offshore wind | 560 | 31 Mar 2029 | Not stated | Scoping |
| Zenobe New Deer Battery Storage | ZENOBE ENERGY LIMITED | Storage | 200 | 31 Oct 2029 | Not stated | Scoping |
| Moray East Offshore Wind Farm | MORAY OFFSHORE WINDFARM (EAST) LIMITED | Offshore wind | 0 | Connected | Not stated | Built |
Left the register since January 2021: North Sea Offshore Wind Farm (1.5 GW).
Recent changes
- Green Volt Offshore WindfarmNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY LIMITED to Green Volt Offshore Windfarm Ltd
- Green Volt Offshore WindfarmNorth Scotland, Offshore windStage 1: Capacity changed from 0 MW to 300 MW
- Green Volt Offshore WindfarmNorth Scotland, Offshore windStage 1: Connection date moved from 1 Apr 2028 to 31 Mar 2029 (+12 months)+12 mo
- Green Volt Offshore WindfarmNorth Scotland, Offshore windStage 2: Capacity changed from 300 MW to 260 MW
- Green Volt Offshore WindfarmNorth Scotland, Offshore windStage 2: Connection date moved from 31 Mar 2029 to 31 Oct 2033 (+55 months)+55 mo
- Green Volt Offshore WindfarmNorth Scotland, Offshore windStage removed (0 MW from 31 Oct 2029)
- Green Volt Offshore WindfarmNorth Scotland, Offshore windStage removed (260 MW from 31 Oct 2033)
- Green Volt Offshore WindfarmNorth Scotland, Offshore windNew stage added (0 MW from 1 Apr 2028)
- Green Volt Offshore WindfarmNorth Scotland, Offshore windNew stage added (0 MW from 31 Oct 2029)
- Green Volt Offshore WindfarmNorth Scotland, Offshore windNew stage added (260 MW from 31 Oct 2033)
- Green Volt Offshore WindfarmNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
- Green Volt Offshore WindfarmNorth Scotland, Offshore windConnection point changed from Green Volt 220/66kV Offshore Substation to New Deer 400kV Substation
- Green Volt Offshore WindfarmNorth Scotland, Offshore windTechnology changed from Offshore wind to Demand, Offshore wind
- Green Volt Offshore WindfarmNorth Scotland, Offshore windConnection point changed from New Deer 400kV Substation to Green Volt 220/66kV Offshore Substation
- Green Volt Offshore WindfarmNorth Scotland, Offshore windConnection date moved from 31 Oct 2029 to 31 Mar 2029 (−7 months)−7 mo
- Green Volt Offshore WindfarmNorth Scotland, Offshore windRenamed from Whirlwind Offshore Wind Farm
- Green Volt Offshore WindfarmNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY LIMITED to FLOTATION ENERGY PLC
- North Sea Offshore Wind FarmNorth Scotland, Offshore windLeft the register (1,500 MW from 31 Oct 2033)1,500 MW
- Green Volt Offshore WindfarmNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
- Zenobe New Deer Battery StorageNorth Scotland, StorageAdded to the registerNew
- Moray East Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Peterhead to New Deer 400kV Substation
- Green Volt Offshore WindfarmNorth Scotland, Offshore windAdded to the registerNew
- Moray East Offshore Wind FarmNorth Scotland, Offshore windRestructured from 2 stages (300 MW from 1 Jul 2021, 600 MW connected) to 1 stage (900 MW connected)
- North Sea Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
- Moray East Offshore Wind FarmNorth Scotland, Offshore windStage 1: 600 MW now connectedConnected
- Moray East Offshore Wind FarmNorth Scotland, Offshore windStage 1: Status changed from Consents Approved to Built
- Moray East Offshore Wind FarmNorth Scotland, Offshore windStage 1: Connection date moved from 7 May 2021 to 12 May 2021 (5 days later)
- Moray East Offshore Wind FarmNorth Scotland, Offshore windStage 1: Connection date moved from 1 Apr 2021 to 7 May 2021 (+1 month)+1 mo
- Moray East Offshore Wind FarmNorth Scotland, Offshore windStage 1: Connection date moved from 4 Jan 2021 to 1 Apr 2021 (+3 months)+3 mo
- Moray East Offshore Wind FarmNorth Scotland, Offshore windStage 2: Connection date moved from 7 Jan 2021 to 1 Jul 2021 (+6 months)+6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose