Moray East Offshore Wind Farm
MORAY OFFSHORE WINDFARM (EAST) LIMITED at New Deer 400kV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 19 Mar 2014
Scottish Government (S36) · Source: REPD - Contract for Difference
- Allocation Round 2
- Technology
- Offshore wind
- Total capacity
- 900 MW
- Connected now
- 900 MW
- Still to connect
- 0 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000533
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Dec 2021 registerConnection point changed from Peterhead to New Deer 400kV Substation
- 30 Jul 2021 registerRestructured from 2 stages (300 MW from 1 Jul 2021, 600 MW connected) to 1 stage (900 MW connected)
- 29 Jun 2021 registerStage 1: 600 MW now connected
- 29 Jun 2021 registerStage 1: Status changed from Consents Approved to Built
- 28 May 2021 registerStage 1: Connection date moved from 7 May 2021 to 12 May 2021 (5 days later)
- 30 Mar 2021 registerStage 1: Connection date moved from 1 Apr 2021 to 7 May 2021 (+1 month)
- 26 Feb 2021 registerStage 1: Connection date moved from 4 Jan 2021 to 1 Apr 2021 (+3 months)
- 26 Feb 2021 registerStage 2: Connection date moved from 7 Jan 2021 to 1 Jul 2021 (+6 months)
Also at New Deer 400kV Substation
Substation view2 other projects, 760 MW still to connect at this substation in total.